Checklist and tooling pointers for database migrations on mobile and backend projects, with a safe rollout sequence.

Use with AI

1Mobile

macOS / iOS:

Android

2Backend

  • Su dung migration tool tuy ngon ngu
    • Go: sql-migrate
    • Elixir: ecto

3Tips / best practices checklist

  • Luon viet migrate up / down
  • back up before migration
  • data validation & repair
  • Prefer ORM migration tool
  • Do not deploy the code first: Do not deploy the code first that write to new columns, and then run the migration. It will only result in errors as the code might try to access non-existing column(s).
  • Ensure the new changes work before you drop anything
  • Use Feature Flags whenever possible

4Safe rollout sequence

For a schema change on a live system, split it into steps that each work with both the old and the new code. This is often called expand, migrate, contract.

1. Expand            2. Deploy code        3. Backfill
add new column  -->  that writes both  -->  old rows
(nullable)           columns
                                              |
5. Contract          4. Deploy code           |
drop old column <--  that reads and   <-------+
(later release)      writes only the
                     new column

Each step is its own migration or deploy, so each can be rolled back on its own.

4.1Example: rename users.name to users.full_name

The SQL below is PostgreSQL. Adapt the syntax to your database.

-- 1. Expand (up)
ALTER TABLE users ADD COLUMN full_name text;

-- 3. Backfill (run in batches on large tables)
UPDATE users SET full_name = name WHERE full_name IS NULL AND id BETWEEN 1 AND 10000;

-- 5. Contract (a later release, after nothing reads or writes "name")
ALTER TABLE users DROP COLUMN name;
-- Down for step 1
ALTER TABLE users DROP COLUMN full_name;

4.2Before you run it

  • Both an up and a down migration exist, and the down one was run on a copy of the data.
  • A verified backup was taken, and you know how long a restore takes.
  • Long locks were checked. On large tables, add indexes concurrently where the database supports it.
  • The migration ran on a staging copy with production-sized data.
  • The step after deploy is a data check (row counts, nulls), not just "no errors".