Resource Assignment

With the nature of consulting team, one member could be assigned to multiple projects at once or handle the work of a member in one project that take more than 100% of his/her time per week.

Based on the Quality Software Management book of Gerald Weinberg, the resource context switching cost is shown as below:

The column “Loss to Context Switching” is a total loss for your productivity. Therefore, one person should only be assigned to maximum 3 projects at the same time, and the total working hour of that person should NOT exceed 120% (meaning not more than 12 hours per day).

It’s the management job to prevent the situation from happening so that we can: